They indicate when the project is current and provide the most accurate projection of the project’s completion.
#SCHEDULE PROJECTS TASKS UPDATE#
#SCHEDULE PROJECTS TASKS FREE#
Task C has a free float of 5 days and a total float of 10 days.Task B has a free float of 5 days and a total float of 5 days,.Task A has no free float and a total float of 5 days,.The following image depicts a typical Task Network Diagram: The baseline may evolve, but only under strict conditions as it’s integrated with the approved scope and budget.Ī Project Schedule can be represented in a Task Network Diagram, which maps the sequence of tasks and their dependencies. This way, it serves as a measure of project performance. Throughout the project, the schedule allows task progress to be measured against the baseline and future tasks to be re-forecasted accordingly. To consolidate the forecast of expense over time (the budget), which will support project cost control.the project float (called total float), which is the gap between the sequencing of the most important project tasks with the longest duration (the critical path) and the objective,.To identify how much time is flexible for these objectives to be met (float), and.To ensure the project objectives are met on time,.
.png)
The resulting “network” of tasks then becomes the basis of scheduling analysis. These tasks are connected by links called dependencies. The schedule consists of all the tasks, or activities, necessary to complete the project deliverables. This also allows for estimating the resources needed on the project and thus consolidating a budget.

This is a detailed plan of the tasks or activities to be carried out over the time frame of the project. The schedule is closely tied to the definition of work to complete therefore, its structure is aligned to the organization of this work, that is to say, the WBS (Work Breakdown Structure). The project schedule is a detailed plan defining how and when the project will deliver its products and services as defined by the project scope.